Mark Huckvale (M.Huckvale@ucl.ac.uk)
Thu, 02 Dec 1999 21:40:46 +0000
Dear All
A second attempt at calculating the total number of person months
to divide between work packages:
4 RAs @ 3 years = 12 man years
6 PIs & 0.5 years = 3 man years
Total 15 man years (180 man months)
This is on the assumption we each work 1/6 time on the project (i.e. about
6 hours in 37.5 hour week). I am a little worried about putting all this
time into work packages, because quite of lot of those 6 hours will be
management. We could introduce a management work package.
So we now have something like:
Materials 2.0 my
Measurement 2.5 my
Modelling 2.5 my
Implementation 2.5 my
Evaluation 3.5 my
Dissemination 1.5 my
Management 0.5 my
Comments?
Mark